Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

n2doc

(47,953 posts)
Mon Jul 31, 2017, 02:28 PM Jul 2017

South Carolina Abandons Nuclear Power Plant Project

BY SAMMY FRETWELL


JULY 31, 2017 12:50 PM

COLUMBIA, SC
After working nine years to expand a nuclear power plant in South Carolina, Santee Cooper and SCE&G said Monday they are pulling out of the $14 billion reactor project in Fairfield County in the wake of rising costs, falling demand for energy, construction delays and the bankruptcy of lead contractor Westinghouse this past spring.

SCE&G said in a news relase that a comprehensive review of the Fairfield County nuclear project — a review that began after Westinghouse filed for bankruptcy — caused the company to conclude that finishing the two nuclear reactors “would be prohibitively expensive.”

“We arrived at this very difficult but necessary decision following months of evaluating the project from all persectives,” SCANA Chairman and CEO Kevin Marsh said in the news release.

He said several factors beyond the company’s control have changed since the construction project was launched, including the Westinghouse bankruptcy. Still,. SCANA had considered building just one of the reactors, but rejected that plan after Santee Cooper withdrew from the project.

Read more here: http://www.thestate.com/news/local/article164544862.html#storylink=cpy

6 replies = new reply since forum marked as read
Highlight: NoneDon't highlight anything 5 newestHighlight 5 most recent replies
 

tonyt53

(5,737 posts)
1. Some of the project can be salvaged by using the turbines and generators in a combined cycle gas
Mon Jul 31, 2017, 02:33 PM
Jul 2017

plant.

SCantiGOP

(13,862 posts)
2. Another utility mothballed a nuke plant decades ago
Mon Jul 31, 2017, 04:16 PM
Jul 2017

They used the containment vessel that had been built to film the movie "The Abyss." After about 20 years, they are now finishing it. So yes, they will likely use the equipment but the huge expense of the site work will be there in the event they want to go back to the project later.
Ironically, the reason the two utilities committed to the project years ago was that the forecast was that natural gas would not be an affordable or reliable source for power plants. So it's anyone's guess (or expert opinion) as to what the situation may be in 10 years.

kristopher

(29,798 posts)
3. That isn't accurate.
Mon Jul 31, 2017, 08:31 PM
Jul 2017

These plants were predicated on pure hopium. The nuclear lobby's planning effort was predicated on at least ten proof of concept plants in the initial wave and there were supposed to be lots more following behind those.

Lots and lots of analysts predicted exactly the economic quagmire that they got themselves into - included among those analysts were all those other planning efforts that were happening at the same time SC and GA were pushing forward.

Massacure

(7,512 posts)
4. The low cost of natural gas caught a lot of utilities by surprise
Mon Jul 31, 2017, 10:57 PM
Jul 2017

It seems to me that I've seen a couple articles over the last few years about coal power plants being scrapped. In fact, I remember an article a couple weeks ago about a company spending several billion dollars on a recently completed coal plant and now they are converting it to natural gas.

Kolesar

(31,182 posts)
5. I don't know who gets stuck with the stranded cost
Mon Jul 31, 2017, 10:57 PM
Jul 2017
https://www.bloomberg.com/news/articles/2017-07-31/scana-to-cease-construction-of-two-reactors-in-south-carolina

“I’m sure there will be customer outrage,” Stacy Nemeroff, a Princeton, New Jersey-based analyst for Bloomberg Intelligence said by phone Monday. “The regulators have been pretty accommodating about delays and cost overruns, but how they’ll deal with a canceled project is unclear.”

mackdaddy

(1,522 posts)
6. Well I think it will be like always, The Ratepayers get stuck with the bill...
Tue Aug 1, 2017, 11:13 AM
Aug 2017

Not the investors, and certainly not the executives behind all of this.

Here in Ohio we ratepayers get to pay for two unprofitable coal burners just this year. And we got to pay for the extra billions for the Zimmer "nuclear" plant near Cinnci that was so poorly built it could never be approved for nuclear so they put a coal burner in. We rate payers got stuck holding the bag.

https://en.wikipedia.org/wiki/William_H._Zimmer_Power_Station

Latest Discussions»Issue Forums»Environment & Energy»South Carolina Abandons N...