British nuclear plant needs 90 years for decommissioning after 26 years in operation
British nuclear plant needs 90 years for decommissioning after 26 years in operation
Mainichi
GWYNEDD, Wales -- The Trawsfynydd Power Station in western Wales in Britain is one of the world's most advanced nuclear power plants when it comes to decommissioning work. It had two gas-cooled reactors with a combined output capacity of 235,000 kilowatts.
The operator of the power station started decommissioning the power plant in 1993. A senior official in charge of the decommissioning work says 99 percent of radioactive materials have been removed. But it will still take 70 more years for the operator to finish decommissioning the nuclear plant.
The Mainichi witnessed firsthand the ongoing decommissioning operation of the plant in Wales, which is taking a lot of time and at huge cost, and got a reminder of the tough road ahead for Japan to decommission the crippled Fukushima No. 1 Nuclear Power Plant in the aftermath of the 2011 Great East Japan Earthquake and tsunami.
Two concrete buildings cover the nuclear reactors in Wales, which sit by a manmade lake.
Magnox Ltd....
http://mainichi.jp/english/english/newsselect/news/20130819p2a00m0na019000c.html