By the way, they are finally almost ready to demolish the Trojan cooling tower...
Description: The only nuclear power plant in Oregon shut down twenty years early, after a cracked steam tube released radioactive gas into the plant, in 1992. It cost $450 million to build the plant, and it is expected to cost the same amount, at least, to finish decommissioning the plant. In 2001, the 1,000 ton 1,130 megawatt reactor was encased in concrete foam, and coated in blue shrink-wrapped plastic, then shipped up the Columbia River on a barge to the Hanford Nuclear Site in Washington, where it was placed in a 45 foot deep pit, and covered with six inches of gravel, making it the first commercial reactor to be moved and buried whole. The plant went on line in 1976, and was said to have been built on an Indian burial ground. When it shut down 16 years later, it was the largest commercial reactor to be decommissioned. Once the rest of the plant is cleaned up and decontaminated, it will probably be demolished, and the 500 foot tall cooling tower will be imploded, but probably not before the spent fuel rods are removed, as, like all the other 108 or so commercial reactors in the country, the radioactive spent fuel is stored on site in a pool, in this case right next to the Columbia River, awaiting the possible opening of the Yucca Mountain radioactive storage facility in Nevada.
http://ludb.clui.org/ex/i/OR3142/Lots of issues. Oregonians finally voted to not allow nuclear power in the state.
http://en.wikipedia.org/wiki/Trojan_Nuclear_Power_PlantIn 1978, the plant was closed for nine months while modifications were made to improve its resistance to earthquakes, following discovery both of major building construction errors and of the close proximity of a previously unknown faultline. The operators sued the constructors, and an undisclosed out of court settlement was eventually made.
The Trojan steam generators were designed to last the life of the plant, but it was only four years before trouble was first detected, as premature cracking of the steam tubes. In 1992, rupture of a steam tube finally closed the plant, and it was announced that replacement of the steam generators would be necessary before it could restart.
Environmental opposition dogged Trojan all of its life, including violent clashes both inside and outside the boundary fence. In an Oregon state poll in 1980, a proposal to ban construction of further nuclear power plants in the state was approved by voters. Then in 1986, a proposal by Lloyd Marbet for immediate closure of the Trojan plant was defeated. This proposal was resubmitted in 1990, and again in 1992 when a competing proposal by Jerry and Marilyn Wilson to close the plant was also included. Although all of these closure proposals were defeated, in campaigning against them the plant operators committed to successively earlier closure dates for the plant.
more at the link...
the spent fuel is sitting there, underground, still waiting to go to Yucca Mtn.
The cooling tower is to be demonlished via dynamite explosion on May 21, 2006.