http://www.latimes.com/news/printedition/front/la-na-halliburton29oct29,1,4288990.story?coll=la-headlines-frontpage Halliburton Contracts Bypassed Objections
By T. Christian Miller Times Staff Writer October 29, 2004
WASHINGTON — <snip>Bunnatine Greenhouse, the Corps of Engineers' chief contracting officer, questioned a decision by commanders to award a contract extension to Halliburton, the oil services company run by Dick Cheney until he became vice president, without the competitive bidding designed to protect U.S. taxpayers. <snip>
"I cannot approve this," Greenhouse wrote on one version of the proposal that is filled with her handwritten scrawls such as "Incorrect!"; "No! How!"; and "Not a valid reason."
Greenhouse, who was threatened with demotion after raising objections to the Halliburton contract, sent her complaints to acting Army Secretary Les Brownlee. Portions of her letter to Brownlee were obtained by Time magazine last week.
The Times has obtained previously undisclosed documents describing the nature of her objections to the Halliburton contract and e-mail discussions among Army Corps officials.
Despite Greenhouse's objections, the Army Corps on Oct. 8 awarded Halliburton the $165-million extension allowing Halliburton's subsidiary KBR to continue providing logistics services to troops stationed in the Balkans.
The final approval did not carry Greenhouse's signature, as normally required by contracting regulations. Instead, it was signed by her assistant, Lt. Col. Norbert Doyle, according to the documents.<snip>