Upstream OnlineNoah Brenner, Anthony Guegel, Jonathan Davis & Anthea Pitt 28 May 2010 00:25 GMT
BP has stopped drilling one of the relief wells to intercept the blown out Macondo bore so it can ready the rig's blowout preventer (BOP) to go on top of the crippled Macondo BOP.
Transocean boss Steve Newman told analysts today that Transocean semi-submersible rig Development Driller II had stopped drilling while BP tries a top kill to try to halt the flow of the Macondo well.BP spokesman David Nicholas told UpstreamOnline that the rig was stopped so its BOP would be ready if needed.
"The (Developmen Driller II) has temporarily suspended drilling operations in preparation for the possible future deployment of its BOP on top of the (Macondo) BOP," he told UpstreamOnline in an email response.
"This is a possible future option for stopping flow from the well and, as throughout, we are advancing options in parallel."
BP operations boss Doug Suttles confirmed that the BOP was being prepped to be deployed but said that it had been at the ready since the beginning of the top kill operation and it was not a sign that BP thought the top kill would not work. more: